Awaab’s LawAwaab’s Law deadline calculator
Enter the date you became aware of a hazard. See each legal deadline as a calendar date, with weekends and bank holidays counted correctly, and the evidence you need at each stage. Based on the regulations and the government guidance that applies from 30 November 2026, covering emergency hazards and significant hazards, including the Phase 2 hazard types.
Work out your deadlines
The clock starts when the landlord becomes aware of a potential hazard. That is usually the day a tenant, contractor or member of staff reports it.
What the law requires, and by when
These duties sit in the Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025. They are implied into almost every social housing tenancy, so a tenant can enforce them in court as a breach of contract.
| Duty | Significant hazard | Emergency hazard |
|---|---|---|
| Investigate | Within 10 working days of becoming aware | Within 24 hours of becoming aware |
| Make the home safe | Within 5 working days of the investigation concluding | Within the same 24 hours |
| Written summary to the tenant | Within 3 working days of the investigation concluding. Not needed if all the required work is finished inside those 3 days, though the tenant must still be told. | |
| Start work to stop it coming back | Begin, or take steps to begin, within 5 working days of the investigation concluding. If that is not reasonably practicable, as soon as it is, and within 12 weeks. | |
| Finish that work | Within a reasonable time. | |
| If the home cannot be made safe in time | Secure suitable alternative accommodation for the household, at the landlord’s expense, until the safety work is done. | |
| Throughout | Keep the tenant informed about timing and progress, and keep records of every step. | |
Three phases, widening the hazards covered
The timescales are the same in every phase. What changes is which hazards they apply to. Emergency hazards of every kind have been covered from the start.
27 October 2025
Phase 1
All emergency hazards, and damp and mould that presents a significant risk of harm.
30 November 2026
Phase 2
Significant hazards from:
- excess cold and excess heat
- falls
- structural collapse
- fire and explosions
- electrical hazards
- domestic hygiene, personal hygiene and food safety
Expected 2027
Phase 3
The remaining hazards in the Housing Health and Safety Rating System, apart from overcrowding.
If you already knew about a hazard before the rules covered it, the timescales start when a new concern is reported, or when the hazard materially changes, after that date.
What an independent survey gives you at each stage
Meeting a deadline is one half of compliance. The other half is being able to show what you found, what you decided and why. A report from a surveyor who does not sell repairs or treatments is evidence a court will give weight to.
The investigation
The cause of the problem, not only its symptoms: condensation, penetrating damp, rising damp or a leak. Moisture readings, dated photographs and a clear statement of whether the hazard is significant or an emergency.
The written summary
Findings in plain English that you can pass to the tenant: whether a hazard was found, what action is needed, and realistic target dates for starting and finishing it.
Making the home safe
A short list of immediate measures for the first five working days, separated from the longer-term repair so that nothing urgent waits on a full specification.
Stopping it coming back
A prioritised schedule of the work that deals with the cause. Your contractor prices against it, and you can check the finished work against it.
If it is ever challenged
A dated, independent record of what was known and when. This supports the defence that the landlord used all reasonable endeavours to comply.
See what our Awaab’s Law surveys cover.
How this calculator counts the days
Day 1 is the next day
Each working-day period starts on the day after the event that triggers it. A hazard reported on a Monday must be investigated by the Monday two weeks later, if there are no bank holidays in between.
Working days
Saturdays, Sundays, Christmas Day, Good Friday and bank holidays in England are not working days. The calculator holds the bank holidays for 2025 to 2028.
24 hours means 24 hours
The emergency period runs on the clock from the moment the landlord becomes aware. It does not pause overnight, at weekends or on bank holidays.
Twelve weeks
The longstop for starting preventative work is counted as 84 calendar days from the day the investigation concludes.
Awaab’s Law deadlines: common questions
How long does a social landlord have to investigate under Awaab’s Law?
For a significant hazard, the investigation must conclude within 10 working days of the landlord becoming aware of it. For an emergency hazard, the landlord must investigate and make the home safe within 24 hours.
When does the clock start?
When the landlord becomes aware of a potential hazard. That is usually the day a tenant, contractor or member of staff reports it. Working-day periods start counting from the next day.
Do weekends and bank holidays count?
Not for the working-day deadlines: Saturdays, Sundays, Christmas Day, Good Friday and bank holidays in England are left out. The 24-hour emergency period is different. It runs on the clock and does not pause overnight, at weekends or on bank holidays.
When must the tenant get a written summary?
Within 3 working days of the investigation concluding. It must say whether a hazard was found, what action will be taken and when, and how to contact the landlord. It is not needed if all the required work is finished within those 3 days, though the tenant must still be told.
Which hazards does Awaab’s Law cover?
Since 27 October 2025 it has covered all emergency hazards, and damp and mould that presents a significant risk of harm. From 30 November 2026, Phase 2 adds significant hazards from excess cold and heat, falls, structural collapse, fire and explosions, electrical hazards and domestic hygiene. Phase 3, expected in 2027, covers the remaining HHSRS hazards apart from overcrowding.
Does Awaab’s Law apply to private landlords?
Not yet. It applies to social landlords in England. The Renters’ Rights Act 2025 contains powers to extend it to private rented homes, but no start date has been confirmed. Read more in our guide to Awaab’s Law for private landlords.
Where this comes from
- Awaab’s Law in the social rented sector, GOV.UK collection, including the regulations.
- Awaab’s Law Phase 2: guidance for social housing landlords, GOV.UK. Applies from 30 November 2026.
- Awaab’s Law Phase 1: guidance for social landlords, GOV.UK. In effect until 29 November 2026.
- UK bank holidays, GOV.UK.
Last checked against the published guidance in November 2026. This calculator is general information to help you plan. It is not legal advice. The regulations themselves decide what is required, and a court decides whether they have been met. Shorter legal timescales, such as those for gas leaks, take priority where they apply. For background, read our guides to the Awaab’s Law timeline and Awaab’s Law in practice.